Politically speaking, GENCO is the acronym for the generating companies in Nigeria and was derived after the unbundling of the power sector. They are licensed with the responsibility to produce electricity for both commercial, industrial and residential users in the country and presently, we have largely two generation mix of hydro and thermal stations.
GENCOs
have been doing their best since they came on board and it can be argued that
the huge investment recorded by these plants is one of the gains of the 2013 privatization
program of the President Goodluck Jonathan’s administration as many stations have
resuscitated or upgraded some of their machines that were not available before
the exercise. Egbin revived ST6; Kainji restored their 1G5 while other stations
like Transcorp, Ughelli upgraded GT15 and Geregu phase 1 carried out massive maintenance
of their generators.
With these achievements, more still need to be done to increase available generation capacity. A major constraint to actualizing this lofty dream is the illiquidity in the sector with the level of revenue collection for energy delivered still very low.
The table below represents the percentage machine availability of installed units versus available units at 0600Hrs of some selected dates.
T able
Showing Percentage Machine Availability of Installed Units versus Available
Machines
With these achievements, more still need to be done to increase available generation capacity. A major constraint to actualizing this lofty dream is the illiquidity in the sector with the level of revenue collection for energy delivered still very low.
The table below represents the percentage machine availability of installed units versus available units at 0600Hrs of some selected dates.
S/N | DATE | NO OF UNITS INSTALLED | AVAILABLE UNITS | PERCENTAGE MACHINE AVAILABILITY (%) |
1 | 16/02/2023 | 162 | 66 | 40.7 |
2 | 18/02/2023 | 162 | 63 | 38.8 |
3 | 19/02/2023 | 162 | 65 | 40.1 |
4 | 24/02/2023 | 162 | 63 | 38.8 |
5 | 26/02/2023 | 162 | 64 | 39.5 |
6 | 27/02/2023 | 162 | 67 | 41.3 |
7 | 20/03/2023 | 162 | 64 | 39.5 |
8 | 21/03/2023 | 162 | 66 | 40.7 |
9 | 25/03/2023 | 162 | 65 | 40.1 |
10 | 27/03/2023 | 162 | 58 | 35.8 |
11 | 28/03/2023 | 162 | 61 | 37.7 |
12 | 29/03/2023 | 162 | 65 | 40.1 |
13 | 03/04.2023 | 162 | 64 | 39.5 |
14 | 05/04/2023 | 162 | 60 | 37.0 |
15 | 06/04/2023 | 162 | 62 | 38.3 |
16 | 07/04/2023 | 162 | 63 | 38.8 |
17 | 08/04/2023 | 162 | 60 | 37.0 |
18 | 09/04/2023 | 162 | 62 | 38.3 |
19 | 10/04/2023 | 162 | 62 | 38.3 |
20 | 11/04/2023 | 162 | 65 | 40.1 |
The table
above shows that out of the 162 installed generators in the power sector in
Nigeria, the percentage availability of installed machines versus available
machines is below 50% and there are many technical reasons for this situation.
While some of the installed machines are out on preventive maintenance and
general overhaul, others are out for reasons like faults, water management, gas
constraints, pre-commissioning tests etc.
Since GENCOs are mandated to generate adequate electricity for the country, it will be good if they put in more efforts to make more machines available to effectively carryout this important responsibility.
Since GENCOs are mandated to generate adequate electricity for the country, it will be good if they put in more efforts to make more machines available to effectively carryout this important responsibility.
The
government have their own role to play towards the improvement of the
percentage machine availability of installed machines versus available units by
way of assisting the sector to recover debts owed by MDAs and other government
parastatals and also reviewing the national gas policy to improve gas
availability for local use, which will in turn lead to increase in electricity
generation, reduce unemployment and improvement in the quality of life of
Nigerians.